HOME PAGE ABOUT US CONTACT US SUBSCRIBE ADVERTISE ARCHIVES
TOP STORIES NATION ECONOMY COMPANIES SHIPPING OPINION PERSPECTIVE LIFE SPORTS BANKING
SEARCH ENGINE
WWWOur Site
Anchored by Jonathan dela Cruz, Salvador Escudero, Boying Remulla, Teddy Boy Locsin and Alvin Capino
Monday to Friday
8:00pm-10:00pm

ARTICLE SERVICES
  • bookmark this page
  • print this article
  • view archive
  • CA voids Japan development award
     
    By Joel R. San Juan
    Reporter
     

    THE Court of Appeals (CA) has granted the petition of Urban Corp. to declare null and void the award by the Department of Finance (DOF) to Nagayama Taisei Consortium (NTC) of the contract to develop the Nampeidai Property of the Philippine government in Tokyo, Japan.

    In a 19-page decision by Associate Justice Apolinario Bruselas Jr., the appellate court’s Special Eighth Division held that the award of the project to NTC should be nullified as it was issued with grave abuse of discretion amounting to excess of jurisdiction.

    The CA reinstated with modification the August 22, 2007, original decision of Judge Vedasto Marco of the Regional Trial Court in Manila canceling the award of the contract to NTC, specifically for violating the provisions of Republic Act 9184, or the Government Procurement Reform Act.

    “It is the public respondents who have violated the clear mandate of RA 9184…as well as rudimentary rules of fair play, due process and the public nature of the award process, by their failure to seasonably inform the petitioner about the turnaround in the project award, or the reasons therefore that were kept secret.”

    The Nampeidai property is one of three Philippine properties in Japan that have been offered to investors under a build-operate-transfer scheme.

    The public bidding, under the Government Procurement Reform Act or Republic Act 9184, was held by the BAC, which declared Nagayama the
    winning bidder after it offered to construct a ¥1.7-billion building on the property and pay the Philippine government an additional ¥480-million.

    In its ruling, the CA also deleted the lower court’s directive for the Head of the Procuring Entity “to issue a notice of award” of the Nampeidai Project to petitioner Urban.

    However, the appeals court did not rule on whether the project should be given to Urban or not.

    “In a procurement process (bidding) controversy, courts may only determine whether or not the procedures laid down by law have been observed; and if not so observed, declare such fact to be so on grounds of grave abuse of discretion, nullifying in the process acts so take in excess of jurisdiction. Courts may not go further to award any contract,” the CA said.

    The CA said the award of the project to NTC suffered “from transparency issues” as the DOF, BAC and NTC short-circuited the process to ease out Urban, which clearly won the bidding.

    Based on the records, several bidders submitted development proposals to the BAC which include Daiwa Jisyo-Mabuchi-Sakura, Urban, NTC and CHKEN Corporatio. They were later deemed qualified for the bidding.

    On November 28, 2003, the BAC declared Urban the winning bidder with the lowest calculated responsive bid.

    In calculating the bidders’ PV, Urban Corp.’s proposal of lowest calculated responsive bid, as required under Section 37 of RA 9184 emerged more favorable to the government, with Y466.6-million with three months’ maturity date or maximum period of payment, as opposed to NTC’s Y464.2-million with a 30-day maturity. Thus, Urban was awarded the project.

    However, neither the Office of the President nor the DOF as head of the procuring entity, officially acted on BAC’s recommendation, in violation of Section 37 of RA 9184. Such inaction meant that the project shall be deemed as approved, pursuant to Section 37 and 38 of the procurement law.
    Meanwhile, the NTC wrote a series of letters to the DOF and BAC seeking a re-evaluation of the PV of its gross bid price based on its offer to pay within a shorter period

    In a letter on March 1, 2006, Teves officially told Urban that the project had been awarded to the NTC as early as June 16, 2005, prompting the aggrieved bidder to file a petition for certiorari before the Pasay Court.

    The NTC also reiterated in its subsequent letters that its “clarification” of its offer to pay the second tranche within 30 days means that it is paying in 7 days, thus, resulting in a better present value computation than Urban’s bid, wherein the second tranche of the latter’s bid is “payable in three months.”

    The BAC initially affirmed Urban’s right to the contract but on June 16, 2005, it favorably resolved NTC’s motion.

    OTHER STORIES

    RP financial system remains effective–BSP


    Global financial crisis will hit OFWs hardest


    Stem the tide of migration to spur growth–economist


    Galoc yields first oil, to fill 6% of demand


    Mixed reactions to ratification of Jpepa


    RP not on Faber’s invest map


    Only P.5B needed to build dairy sector


    Inflation pressures remain in Asean–IMF


    Remittance, exports taps to slow


    CA voids Japan development award