|
LOOKING
at ensuring energy security in the
Luzon grid by 2010 and 2011, Korea Electric Power Corp. (Kepco)
has expressed willingness to possibly work with TeaM
Energy Corp. in expanding the 1,200-megawatt Ilijan
natural gas-fired power plant in Batangas.
TeaM
Energy is the project company of CrimsonPower Holdings
Co. Inc., the consortium led by Tokyo Electric Power Co.
Inc. and Marubeni Corp. which acquired the assets and
business of Mirant Corp. in the Philippines.
A source
privy to the issues told reporters that Kepco is open
take in TeaM Energy as its partner in expanding the
Ilijan expansion by 300 megawatts, considering that TeaM
Energy already has a 20-percent stake in Ilijan.
TeaM
Enegy president Federico E. Puno earlier said his
company plans to discuss with the existing consortium
operating the 1,251-megawatt Ilijan natural gas-fired
power plant to determine the probability of expanding
its capacity by another 600 megawatts. He added,
however, that the expansion of Ilijan depends on where
the around 300-megawatt San Pascual power purchase
agreement (PPA) goes.
Napocor
has yet to decide where it will attach the San Pascual
PPA project or if it will just put up an option that
whoever wants to build the plant will have to bid for
the said contract.
“If and
when we get the San Pascual, then we have around 300
megawatts of contracted power off-take to Napocor, while
the balance will be done on a merchant plant basis,” he
added.
“There
is also and always a need to expand the Ilijan looking
on the longer-term to have new capacity by 2010 or 2011
[the critical period for Luzon],” the TeaM Energy
official said.
The
source agreed that Kepco is also waiting for the Power
Sector Assets and Liabilities Management Corp. (PSALM)
to finally decide when it will bid out the San Pascual
power purchase agreement (PPA) before it expands the
Ilijan by 300 megawatts.
“We are
still waiting for the decision from PSALM, but based on
the Department of Justice’s legal opinion, the PPA
should be bid out competitively,” the source said.
The San
Pascual project was supposed to take up the remaining
300 megawatts from the 3,000-megawatt Malampaya
deep-water gas to power project.
The
2,700 megawatts were distributed to 1,200-megawatt
Ilijan power plant; the Lopez-owned 1,000-megawatt Sta.
Rita power plant; and the 500-megawatt San Lorenzo power
plant.
The
construction of San Pascual plant did not push through
with the excess capacity in the power system during that
time. However, the proponents of the San Pascual had
then signed a PPA with Napocor.
Based on
the plan, PSALM will buy out the 25-year PPA contract of
Napocor with San Pascual and assign the contract to
Sucat power plant.
The
Sucat power plant is envisioned to be converted into a
gas-fired power facility, and the government has been
working out the pretermination of the contract of San
Pascual with US-based Edison Mission Energy since
September 2002. |